Work Profile Report [55W1956]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/249529/2024-E-File No.-65254/25
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
208.13
Resanction Cost :
208.13
Tentative Cost :
208.13
Exp. Upto Last Fy :
0.13
For CFY 2025-2026
Remaining :
208.00
Demand :
150.00
Allotment :
87.53
Exp in CFY :
87.53
Total Up to Date Exp :
87.66
Construction Started
Sanction on : 9 months 2 weeks ago
24 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
2 %
Up to Date :
83 %
Tentative Completion date on : 9 months 3 weeks from now
31 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.60 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 30-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: