Work Profile Report [55W2042]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1/327147/2025/PWD2-BUD/ANBU/4/2025-III-2-Public Works Department Dt. 02-09-2025
TS Amount (lakhs) : 99.43 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
99.43
Resanction Cost :
99.43
Tentative Cost :
99.43
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
99.43
Demand :
5.00
Allotment :
8.91
Exp in CFY :
8.91
Total Up to Date Exp :
8.91
Construction Started
Sanction on : 4 months 3 weeks ago
02 Sep 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
45 %
Tentative Completion date on : 6 months 1 week from now
31 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.00 कि0मी0 में कार्य पूर्ण, शेष कार्य प्रगति में है। -- as on 31-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: