Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
56W364 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-6668/111 (2)/13-37 (प्रा0आ0)/ 2013 दिनांक 26.11.13
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.88
Resanction Cost :
58.88
Tentative Cost :
58.88
Exp. Upto Last Fy : 35.50
For CFY 2024-2025
Remaining : 23.38
Demand : 23.39
Allotment : 0.00
Exp in CFY : 1.36
Total Up to Date Exp : 36.85
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 50 %
Sanction on :
10 years 7 months ago
26 Nov 2013
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अधीक्षण अभियन्ता के पत्रांक संख्या 557/342 सी0-9/15 दिनांक 11.02.2015 के द्वारा (लं0 6.02 कि0मी0) समरेंखण स्वीकृत हैं शासनादेश संख्या 2385/।।।(2)/21-37(प्रा0आ0)/13 दिनाक 04.08.2021 के द्वारा लागत रू0 28.85 लाख लम्बाई 1.20 किमी0 द्वितीय चरण की स्वीकृत प्राप्त सिविल वन भूमि जिलाधिकारी के पत्रांक संख्या 212/12ए-16-17 (2014-17) के द्वारा स्वीकृति प्राप्त प्रतिकर गणना की कार्यवाही गमितान है। -- as on 06-Apr-2024
Physical Peramenters