Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 7 | 0 |
56W513 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 2477/111(2)/16-15 (मा0मु0घो0)/2016, दिनांक 20.09.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.49
Resanction Cost :
37.49
Tentative Cost :
37.49
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 37.39
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 12 %
Up to Date : 12 %
Sanction on :
7 years 9 months ago
20 Sep 2016
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अधीक्षण अभियन्ता के पत्रांक संख्या 7333/342/25सी0.9/21 दिनांक 27.09.2021 के द्वारा समरेंखण स्वीकृत हैं। वन विभाग द्वारा संयुक्त निरीक्षण कर लिया गया हैं जिसकी आख्या प्राप्त हैं। प्रभावित वनभममि का हस्तानातरण प्रस्ताव गठन की कार्यवाही गतिममान हैं। -- as on 01-Jun-2024
Physical Peramenters