Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
56W614 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-616/।।।(2)/21-01(प्रा0आ0)/2020 दि0 19.03.2021
TS Amount (lakhs) : 228.37 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
228.37
Resanction Cost :
245.50
Tentative Cost :
245.50
Exp. Upto Last Fy : 231.42
For CFY 2024-2025
Remaining : 14.08
Demand : 2.21
Allotment : 2.21
Exp in CFY : 0.00
Total Up to Date Exp : 231.42
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
19 Mar 2021
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
1 year 8 months ago
01 Nov 2022
Remark
Bottelneck: no issue
माह नवम्बर 2023 में भौतिक रूप से से पांच वर्षिय अनुरक्षण कार्य को छोडते हुए कार्य पूर्ण। कार्य अनुरक्षण अवधि में। -- as on 06-Apr-2024
Physical Peramenters