Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
56W614 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-616/।।।(2)/21-01(प्रा0आ0)/2020 दि0 19.03.2021
TS Amount (lakhs) : 228.37 Lacs
Financial Detail
Sanction Cost : 228.37 Lacs
Resanction Cost : 245.50 Lacs
Exp. Upto Last Fy : 231.42 Lacs
For CFY 2024-2025
Remaining : 14.08 Lacs
Demand : 2.21 Lacs
Allotment : 0.55 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 231.42 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 2 months ago
19 Mar 2021
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
माह नवम्बर 2023 में भौतिक रूप से से पांच वर्षिय अनुरक्षण कार्य को छोडते हुए कार्य पूर्ण। कार्य अनुरक्षण अवधि में। -- as on 06-Apr-2024
Physical Peramenters