Work Profile Report [56W625]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 1355/।।।(2)/21-47(प्रा0आ0)2016 दिनांक 20.05.2021
TS Amount (lakhs) : 6.3 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
26.45
Resanction Cost :
26.45
Tentative Cost :
26.45
Exp. Upto Last Fy :
0.96
For CFY 2025-2026
Remaining :
25.49
Demand :
1.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.96
Survey work done
Sanction on : 4 years 6 months ago
20 May 2021
Physical Progress:
At start of FY 2025-2026 :
2 %
Up to Date :
4 %
Tentative Completion date on : 1 year 2 weeks from now
31 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन विभाग एवं राजस्व विभाग के साथ पुनः संयुक्त निरीक्षण किया जाना है। -- as on 09-Dec-2025