Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
56W634 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6037/।।।(2)/21-47(प्रा0आ0)/2016 दिनांक 15.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
445.72
Resanction Cost :
460.96
Tentative Cost :
460.96
Exp. Upto Last Fy : 441.81
For CFY 2024-2025
Remaining : 19.15
Demand : 2.49
Allotment : 2.49
Exp in CFY : 0.00
Total Up to Date Exp : 441.81
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
15 Dec 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 year 2 weeks ago
01 Jul 2023
Remark
Bottelneck: no issue
माह अक्टूबर 2023 में भौतिक रूप से से पांच वर्षिय अनुरक्षण कार्य को छोडते हुए कार्य पूर्ण। कार्य अनुरक्षण अवधि में। -- as on 06-Apr-2024
Physical Peramenters