Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 3.500 | 0 | 0.000 | 0.000 |
56W686 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के ई-पत्रावली संख्या 37518 दिनांक 28.06.2023
TS Amount (lakhs) : 126.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
126.31
Resanction Cost :
135.78
Tentative Cost :
135.78
Exp. Upto Last Fy : 112.87
For CFY 2024-2025
Remaining : 22.91
Demand : 13.44
Allotment : 20.36
Exp in CFY : 9.07
Total Up to Date Exp : 121.94
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 2 weeks ago
27 Jun 2023
Tentative Completion date:
2 months 4 weeks from now
15 Oct 2024
Actual Completion Date:
3 months 3 weeks ago
25 Mar 2024
Remark
Bottelneck: no issue
रू0 42.92 लाख का व्यय राज्य योजना मद से किया गया हैं एवं कार्य नाबार्ड-29 के अन्तर्गत स्वीकृत है। भौतिक रूप से स्वीकृति स्टेज-। का कार्य माह मार्च 2024 को पूर्ण। दायित्व का भुगतान शेष पांच वर्षिय अनुरक्षण भी सम्मलित हैं। एवं उक्त कार्य नाबार्ड के पत्र संख्या राबै उत्त.क्षे.का.एसपीडी-आर-16. आरआईडीएफ-XXIX 127thआईएससी-30.11.2023 के द्वारा नाबार्ड-29 के अन्तर्गत स्वीकृत हैं। -- as on 06-Apr-2024
Physical Peramenters