Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.47 | 2.47 | 2.47 | 0 |
59W1741 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0 698/।।।(2)/19-29(एम.एल.ए.) /2017 दिनांक 18.02.2019
TS Amount (lakhs) : 155.28 Lacs
Financial Detail
Sanction Cost : 155.28 Lacs
Resanction Cost : 165.76 Lacs
Exp. Upto Last Fy : 140.40 Lacs
For CFY 2024-2025
Remaining : 25.36 Lacs
Demand : 2.45 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 140.40 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 3 months ago
18 Feb 2019
Tentative Completion date:
2 years 10 months ago
30 Jun 2021
Actual Completion Date:
2 years 1 month ago
31 Mar 2022
Remark
Bottelneck: no issue
कायपूर्ण 06/2021, कार्य को पुनः उच्चाधिकारियों के निर्देश एवं नाबार्ड की गाईड लाइन के अनुसार 05 वर्ष के रखरखाव हेतु लिया गया है तथा कार्य पर नाबार्ड द्वारा जारी अनुरक्षण लागत को कुल स्वीकृत लागत में जोड़ते हुए पुनःरीक्षित लागत अंकित की गयी है। -- as on 02-May-2024
Physical Peramenters