Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.19 | 4.19 | 4.19 | 0 |
59W1832 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 170/।।।(2)/21-29(एम.एल.ए.) /2017टी0सी0 देहरादून दि0 04.02.2021
TS Amount (lakhs) : 376.33 Lacs
Financial Detail
Sanction Cost : 376.33 Lacs
Resanction Cost : 404.55 Lacs
Exp. Upto Last Fy : 389.45 Lacs
For CFY 2024-2025
Remaining : 15.10 Lacs
Demand : 2.35 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 389.45 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
04 Feb 2021
Tentative Completion date:
6 months 2 weeks ago
31 Oct 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 12/2023, कार्य को पुनः उच्चाधिकारियों के निर्देश एवं नाबार्ड की गाईड लाइन के अनुसार 05 वर्ष के रखरखाव हेतु लिया गया है तथा कार्य पर नाबार्ड द्वारा जारी अनुरक्षण लागत को कुल स्वीकृत लागत में जोड़ते हुए पुनःरीक्षित लागत अंकित की गयी है। -- as on 02-May-2024
Physical Peramenters