Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.485 | 2.485 | 2.485 | 0 |
59W1910 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2632/।।।(2)/21-29(एम.एल.ए.) /2017टीसी-II देहरादून दि0 11.08.2021
TS Amount (lakhs) : 114.93 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
114.93
Resanction Cost :
123.55
Tentative Cost :
123.55
Exp. Upto Last Fy : 114.93
For CFY 2024-2025
Remaining : 8.62
Demand : 1.55
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 114.93
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
11 Aug 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्यपूर्ण 06/2022, कार्य को पुनः उच्चाधिकारियों के निर्देश एवं नाबार्ड की गाईड लाइन के अनुसार 05 वर्ष के रखरखाव हेतु लिया गया है तथा कार्य पर नाबार्ड द्वारा जारी अनुरक्षण लागत को कुल स्वीकृत लागत में जोड़ते हुए पुनःरीक्षित लागत अंकित की गयी है। -- as on 02-May-2024
Physical Peramenters