Work Profile Report [59W2249]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667/31 दिनांक 07.03.2024
TS Amount (lakhs) : 72.9 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
72.90
Resanction Cost :
72.90
Tentative Cost :
72.90
Exp. Upto Last Fy :
0.17
For CFY 2024-2025
Remaining :
72.73
Demand :
55.00
Allotment :
11.12
Exp in CFY :
11.53
Total Up to Date Exp :
11.70
Construction Started
Sanction on : 8 months 2 weeks ago
07 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand