Work Profile Report [59W2279]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-55435/30 दि0 05.09.2024
TS Amount (lakhs) : 56.65 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.65
Resanction Cost :
56.65
Tentative Cost :
56.65
Exp. Upto Last Fy :
0.28
For CFY 2025-2026
Remaining :
56.37
Demand :
56.00
Allotment :
14.60
Exp in CFY :
14.60
Total Up to Date Exp :
14.88
Construction Started
Sanction on : 10 months 1 week ago
05 Sep 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
40 %
Tentative Completion date on : 2 months 1 week from now
30 Sep 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
600 मीटर लम्बाई में कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 30-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand