Work Profile Report [59W2337]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-50282/28 दि0 09.06.2025
TS Amount (lakhs) : 98.02 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
98.02
Resanction Cost :
98.02
Tentative Cost :
98.02
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
98.02
Demand :
40.00
Allotment :
30.24
Exp in CFY :
30.24
Total Up to Date Exp :
30.24
Construction Started
Sanction on : 6 months 6 days ago
09 Jun 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
29 %
Tentative Completion date on : 2 months 2 weeks from now
02 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
200 मी0 में कार्यपूर्ण, शेष कार्य प्रगति में। -- as on 30-Oct-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: