Work Profile Report [59W2375]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-46667/31 दि0 26.08.2025
TS Amount (lakhs) : 91.88 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
91.88
Resanction Cost :
91.88
Tentative Cost :
91.88
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
91.88
Demand :
50.00
Allotment :
80.00
Exp in CFY :
0.25
Total Up to Date Exp :
0.25
Construction Started
Sanction on : 4 months 4 weeks ago
26 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 3 months 1 week from now
05 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
50 प्रतिशत कार्यपूर्ण, शेष कार्य प्रगति पर है। -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: