Work Profile Report [59W2394]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड़ शासन, लोक निर्माण अनुभाग-2 के ई फाईल संख्या-84756/29 दि0 10.11.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.69
Resanction Cost :
48.69
Tentative Cost :
48.69
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
48.69
Demand :
5.00
Allotment :
0.72
Exp in CFY :
0.72
Total Up to Date Exp :
0.72
Construction Started
Sanction on : 1 month 3 weeks ago
10 Nov 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
10 %
Tentative Completion date on : 7 months 3 weeks from now
25 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0 का कार्य प्रगति में। -- as on 29-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: