Work Profile Report [5W271]

जनपद बागेश्वर में दयोनाई-कोहिना मोटर मार्ग के कन्ठेश्वर मन्दिर से थाकला तक मोटर मार्ग का निर्माण।(प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 5423/।।।(2)/10-18(प्रा0आ0)/2010, दिनांक 27.08.2010

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

12.60

Resanction Cost :

12.60

Tentative Cost :

12.60

Exp. Upto Last Fy :

4.31

For CFY 2025-2026

Remaining :

8.29

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

4.31

Alignment Approved

Sanction on : 14 years 11 months ago

27 Aug 2010

Physical Progress:

At start of FY 2025-2026 :

80 %

Up to Date :

80 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

fवfधवत स्वीकृfत प्राप्त। मुआवजा fवतरण fकया जाना है। fद्वतीय चरण में कार्य पूर्ण। -- as on 27-Oct-2024

Rating : 80

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: