Work Profile Report [5W29]

बागेश्वर में पालड़ीछीना-जनौटीपालड़ी-कराना-पालड़ीचनौली-जैनकरास मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 2454/111-2/05-07(प्रा0आ0)/05टी0सी0 दिनांक 28.10.2005

TS Amount (lakhs) : 146.18 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

187.48

Resanction Cost :

187.48

Tentative Cost :

187.48

Exp. Upto Last Fy :

138.85

For CFY 2025-2026

Remaining :

48.63

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

138.85

Unstarted Work

Sanction on : 21 years 2 months ago

17 Feb 2004

Physical Progress:

At start of FY 2025-2026 :

77 %

Up to Date :

77 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
12
7
7
-

Remark

view all

पुनरीक्षित आगणन मुख्य अभियन्ता, लो0नि0वि0, अल्मोड़ा के पत्रांक 1307/507याता0-अ0/2023, दिनांक 23.04.2023 द्वारा शासन को प्रेषित। -- as on 24-Jun-2023

Rating : 77

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand