Work Profile Report [5W6]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2490/111- 2/08-61 (प्रा0आ0)/ 2007 दि0 25.07.2008
TS Amount (lakhs) : 400.55 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
400.55
Resanction Cost :
400.55
Tentative Cost :
328.39
Saving
72.16
Exp. Upto Last Fy :
306.39
For CFY 2025-2026
Remaining :
94.16
Demand :
17.00
Allotment :
2.00
Exp in CFY :
2.00
Total Up to Date Exp :
308.39
Work completed
Sanction on : 17 years 5 months ago
25 Jul 2008
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
100 %
Tentative Completion date on : 6 years 9 months ago
31 Mar 2019
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मुआवजा वितरण किया जा रहा है। -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand