Work Profile Report [5W668]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 1862/।।।(2)/17-47(एम0एल0ए0) /2017, दिनांक 31.10.2017
TS Amount (lakhs) : 89.95 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.95
Resanction Cost :
813.17
Tentative Cost :
813.17
Exp. Upto Last Fy :
67.68
For CFY 2025-2026
Remaining :
745.49
Demand :
300.00
Allotment :
64.43
Exp in CFY :
64.43
Total Up to Date Exp :
132.11
Construction Started
Sanction on : 8 years 1 month ago
31 Oct 2017
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
5 %
Tentative Completion date on : 10 months 2 days from now
18 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
श्री पुष्कर सिंह धामी, माननीय मुख्यमंत्री उत्तराखण्ड सरकार द्वारा दिनांक 07.12.2025 को शिलान्यास किया गया। -- as on 08-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand