Work Profile Report : 5W668
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 1862/।।।(2)/17-47(एम0एल0ए0) /2017, दिनांक 31.10.2017
TS Amount (lakhs) : 89.95 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.95
Resanction Cost :
813.17
Tentative Cost :
813.17
Exp. Upto Last Fy :
67.68
For CFY 2025-2026
Remaining :
745.49
Demand :
300.00
Allotment :
160.19
Exp in CFY :
160.19
Total Up to Date Exp :
227.87
Construction Started
Sanction on : 8 years 3 months ago
31 Oct 2017
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
5 %
Tentative Completion date on : 8 months 5 days from now
18 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: