Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 5.75 | 4.750 | 1 | 0.000 | 0.000 |
No of Bridges | 2 | 1 | 0 | 1 | 1 | 0 |
5W7 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2490/111- 2/08-61 (प्रा0आ0)/ 2007 दि0 25.07.2008
TS Amount (lakhs) : 282.65 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
517.50
Resanction Cost :
517.50
Tentative Cost :
517.50
Exp. Upto Last Fy : 420.06
For CFY 2024-2025
Remaining : 97.44
Demand : 50.00
Allotment : 50.00
Exp in CFY : 32.00
Total Up to Date Exp : 452.06
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
15 years 11 months ago
25 Jul 2008
Tentative Completion date:
2 months 2 weeks ago
01 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग में विवाद के कारण उच्चाधिकारियों के आदेशानुसार मार्ग की 5.75 किमी0 लम्बाई के स्थान पर 4.75 किमी0 लम्बाई में पार्ट-।, पार्ट-।। का कार्य पूर्ण कर अनुबन्ध का अन्तिमीकरण कर दिया गया है। सेतु कार्य के दाये एवटमेन्ट में 6.50मी0 ऊचाई एवं बाये एवटमेन्ट में 4.50मी0 ऊचाई का कार्य पूर्ण। वर्तमान में सेतु के दाये एवटमेन्ट पहुच मार्ग की दीवार का कार्य प्रगति पर। सेतु के फैब्रीकेशन का कार्य वर्कशाप हल्द्वानी में प्रगति पर। -- as on 21-Jul-2023
Physical Peramenters