Work Profile Report [5W877]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-63177/2022, दिनांक 15.09.2022
TS Amount (lakhs) : 86.61 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
86.61
Resanction Cost :
93.11
Tentative Cost :
63.11
Saving
30.00
Exp. Upto Last Fy :
53.92
For CFY 2025-2026
Remaining :
39.19
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
53.92
In Maintenance After Completion
Sanction on : 2 years 7 months ago
15 Sep 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 2 months ago
03 Mar 2023
Actual Completion Date : 2 years 2 weeks ago
28 Apr 2023
Physical Linear Components
Remark
Overall Saving 30 has been recorded as expected cost of work reduced from 93.11 to 63.11 . -- as on 06-May-2025
Assets :
© PWD Uttarakhand