Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.9 | 3.9 | 0.000 | 3.9 | 3.900 | 0.000 |
5W900 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/111079/2023, ई फाईल संख्या-35078, दिनांक 29.03.2023
TS Amount (lakhs) : 241.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
252.12
Resanction Cost :
252.12
Tentative Cost :
252.12
Exp. Upto Last Fy : 103.08
For CFY 2024-2025
Remaining : 149.04
Demand : 141.00
Allotment : 80.00
Exp in CFY : 10.88
Total Up to Date Exp : 113.96
Construction Started
Physical Progress:
At start of FY 2024-2025 : 33 %
Up to Date : 60 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अतिरिक्त पहाड़ कटान कार्य पूर्ण, स्कपर एवं दीवार निर्माण कार्य प्रगति पर। 3.40 किमी0 जी0-1 एवं 3.10 किमी0 जी0-2 एवं 2.90 किमी0 जी0-3 का कार्य पूर्ण। शेष कार्य प्रगति पर। निविदा कम दरों पर प्राप्त होने के कारण अनुबन्ध में स्वीकृत लागत के सापेक्ष रू0 8.00 लाख की बचत होगी। -- as on 04-Jul-2024
Physical Peramenters