Work Profile Report [60W4]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : NH-28014/01/2014/UR/CRF/NH-2(Zone-1) dated 20-02-2019 (Job No. CRF-UR-2021-22-18 (04 to 28) Uttarakhand Govt. Go 105/III(3)/2020-17(CRF)/19 dt. 15.01.2020
TS Amount (lakhs) : 2374.56 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2151.22
Resanction Cost :
2374.56
Tentative Cost :
2374.56
Exp. Upto Last Fy :
1,363.63
For CFY 2024-2025
Remaining :
1,010.93
Demand :
381.00
Allotment :
641.96
Exp in CFY :
641.96
Total Up to Date Exp :
2,005.59
Work completed
Sanction on : 5 years 10 months ago
20 Feb 2019
Physical Progress:
At start of FY 2024-2025 :
73 %
Up to Date :
100 %
Tentative Completion date on : 6 months 2 weeks ago
10 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
work is in progress. -- as on 10-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: