Work Profile Report [67W333]

सुरपुर-डांडानागराजा मोटर मार्ग के पुरमिसी होते हुए अम्बेडकर ग्राम भूतनिसी तक मोटर मार्ग का नव निर्माण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 1914(1)/।।।(2)/15-08(प्रा0आ0)/2015 दि0 20.03.2015

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

56.25

Resanction Cost :

56.25

Tentative Cost :

56.25

Exp. Upto Last Fy :

34.78

For CFY 2025-2026

Remaining :

21.47

Demand :

0.00

Allotment :

21.47

Exp in CFY :

0.00

Total Up to Date Exp :

34.78

Phase1 DPR Submitted

Sanction on : 10 years 9 months ago

20 Mar 2015

Physical Progress:

At start of FY 2025-2026 :

60 %

Up to Date :

60 %

Tentative Completion date on : 9 months 4 weeks from now

31 Oct 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.000
0.000

Remark

view all

प्रतिकर भुगतान की कार्यवाही की जा रही है। -- as on 29-Jul-2024

Rating : 73

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: