Work Profile Report [67W629]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1706/।।।(2)/21-37(एम0एल0ए0)/2017 टी0सी0-1 दि0 17.06.2021
TS Amount (lakhs) : 70.22 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
70.22
Resanction Cost :
70.22
Tentative Cost :
70.22
Exp. Upto Last Fy :
38.17
For CFY 2025-2026
Remaining :
32.05
Demand :
32.00
Allotment :
0.50
Exp in CFY :
0.50
Total Up to Date Exp :
38.67
Construction Started
Sanction on : 4 years 5 months ago
17 Jun 2021
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
2.00 कि0मी0 पहाड कटान का कार्य पूर्ण। शेष 1.00 कि0मी0 ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 29-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: