Work Profile Report [67W633]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2312/।।।(2)/21-01(प्रा0आ0)2021 दि0 23.07.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
21.86
Resanction Cost :
21.86
Tentative Cost :
21.86
Exp. Upto Last Fy :
4.90
For CFY 2025-2026
Remaining :
16.96
Demand :
0.00
Allotment :
0.10
Exp in CFY :
0.00
Total Up to Date Exp :
4.90
Phase1 DPR Submitted
Sanction on : 4 years 5 months ago
23 Jul 2021
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 2 months 4 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण का कार्य पूर्ण। अवशेष प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand