Work Profile Report [67W637]

घडियाल-पाली-डांगी (शहीद मनीष पटवाल) मोटर मार्ग को कण्डारखोली बैण्ड से तकलना-थनूल तक मोटर मार्ग का नव निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2312/।।।(2)/21-01(प्रा0आ0)2021 दि0 23.07.2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

31.05

Resanction Cost :

31.05

Tentative Cost :

31.05

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

31.05

Demand :

1.15

Allotment :

1.15

Exp in CFY :

1.15

Total Up to Date Exp :

1.15

Phase1 DPR Submitted

Sanction on : 4 years 4 months ago

23 Jul 2021

Physical Progress:

At start of FY 2025-2026 :

5 %

Up to Date :

0 %

Tentative Completion date on : 3 months 2 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
2.5
2.5
0.000
2.5
0.000
0.000
Jobs
3
3
0
3
0
0

Remark

view all

ई-डी0पी0आर0 के माध्यम से आगणन गठित कर प्रेषित कर दिया गया है। -- as on 24-Apr-2025

Rating : 6

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: