Work Profile Report [67W833]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 37510 दि0 23.082024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
182.25
Resanction Cost :
182.25
Tentative Cost :
182.25
Exp. Upto Last Fy :
51.56
For CFY 2025-2026
Remaining :
130.69
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
51.56
Construction Started
Sanction on : 7 months 1 week ago
23 Aug 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
50 %
Tentative Completion date on : 7 months 1 week from now
15 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1,जी-2 का कार्य पूर्ण। जी-3 का कार्य प्रगति पर है। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: