Work Profile Report [67W834]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई पत्रावली सं0 26412 दि0 01.10.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
261.13
Resanction Cost :
261.13
Tentative Cost :
261.13
Exp. Upto Last Fy :
59.98
For CFY 2025-2026
Remaining :
201.15
Demand :
200.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
59.98
Construction Started
Sanction on : 6 months 1 week ago
01 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
45 %
Up to Date :
45 %
Tentative Completion date on : 8 months 1 week from now
20 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1,का कार्य पूर्ण। जी-2 कार्य प्रगति पर है। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: