Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.375 | 2.375 | 0.000 | 2.375 | 2.370 | 2.370 |
68W298 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0-पत्रावाली संख्या 36342 दिनांक 08.09.2023
TS Amount (lakhs) : 160.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
160.07
Resanction Cost :
160.07
Tentative Cost :
160.07
Exp. Upto Last Fy : 30.42
For CFY 2024-2025
Remaining : 129.65
Demand : 80.00
Allotment : 70.00
Exp in CFY : 59.56
Total Up to Date Exp : 89.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 100 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
1 week 4 days ago
06 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । -- as on 06-Jul-2024
Physical Peramenters