Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.375 | 2.375 | 0.000 | 2.375 | 2.370 | 0.000 |
68W298 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0-पत्रावाली संख्या 36342 दिनांक 08.09.2023
TS Amount (lakhs) : 160.07 Lacs
Financial Detail
Sanction Cost : 160.07 Lacs
Resanction Cost : 160.07 Lacs
Exp. Upto Last Fy : 30.42 Lacs
For CFY 2024-2025
Remaining : 129.65 Lacs
Demand : 80.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 30.42 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 40 %
Sanction on :
8 months 1 week ago
08 Sep 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिग का कार्य पूर्ण एंव इण्टर कोट का कार्य प्रगति में है। -- as on 15-May-2024
Physical Peramenters