Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
68W300 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई0-पत्रावली संख्या 36342 दिनांक 30.10.2023
TS Amount (lakhs) : 369.23 Lacs
Financial Detail
Sanction Cost : 369.23 Lacs
Resanction Cost : 369.23 Lacs
Exp. Upto Last Fy : 0.53 Lacs
For CFY 2024-2025
Remaining : 368.70 Lacs
Demand : 248.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 36.10 Lacs
Total Up to Date Exp : 36.63 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 25 %
Sanction on :
6 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
3 weeks 5 days from now
15 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग का कार्य प्रगति पर है। -- as on 27-Mar-2024
Physical Peramenters