Work Profile Report [68W349]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली संख्या 27563 दिनांक 11 फरवरी 2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.86
Resanction Cost :
89.86
Tentative Cost :
89.86
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
89.77
Demand :
75.00
Allotment :
29.69
Exp in CFY :
29.69
Total Up to Date Exp :
29.78
Construction Started
Sanction on : 5 months 3 weeks ago
12 Feb 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
40 %
Tentative Completion date on : 7 months 6 days from now
15 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
टाॅप कोट का कार्य प्रगति पर है। -- as on 02-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: