Work Profile Report [68W352]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई0 पत्रावली संख्या 41863 लोक निर्माण अनुभाग-2 देहरादून दिनांक 11/03/2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
154.78
Resanction Cost :
154.78
Tentative Cost :
154.78
Exp. Upto Last Fy :
0.09
For CFY 2025-2026
Remaining :
154.69
Demand :
41.08
Allotment :
23.23
Exp in CFY :
23.23
Total Up to Date Exp :
23.32
Construction Started
Sanction on : 4 months 4 weeks ago
11 Mar 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
20 %
Tentative Completion date on : 7 months 6 days from now
15 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान का कार्य प्रगति पर है। -- as on 02-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand