Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 24 | 24 | 24 | 0 |
69W280 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 501/111(2)/21-38 (एम0एल0ए0)2017 टी0सी0-11 दिनांक 09 मार्च 2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.71
Resanction Cost :
21.71
Tentative Cost :
21.71
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 21.71
Demand : 5.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 4 months ago
09 Mar 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अधीक्षण अभियन्ता के पत्रांक 4422/1449 याता-12/2021 दिनांक 31.07.2021 द्वारा समरेखण स्वीकृत। वर्तमान में मार्ग में संयुक्त निरीक्षण हेतु मार्ग में लेवल एवं बैक पिलर लगाने का कार्य गतिमान है। -- as on 15-Dec-2023
Physical Peramenters