Work Profile Report [69W292]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 12(1ं)111(2)/21-38 (एम.एल.ए.)2017 टी0सी0 दि0 03.01.2022
TS Amount (lakhs) : 98.84 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
98.84
Resanction Cost :
98.84
Tentative Cost :
98.84
Exp. Upto Last Fy :
2.12
For CFY 2025-2026
Remaining :
96.72
Demand :
70.00
Allotment :
10.00
Exp in CFY :
4.92
Total Up to Date Exp :
7.05
Construction Started
Sanction on : 3 years 7 months ago
03 Jan 2022
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 4 months 1 week ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 06-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: