Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.623 | 0.623 | 0.000 | 0.623 | 0.000 | 0.000 |
69W338 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली सं0 36087 लोक निर्माण अनुभाग-2 दि0 30.06.2023
TS Amount (lakhs) : 43.09 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
43.09
Resanction Cost :
43.09
Tentative Cost :
43.09
Exp. Upto Last Fy : 18.71
For CFY 2024-2025
Remaining : 24.38
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.71
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
1 year 2 weeks ago
30 Jun 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
G1,G2,G3 का कार्य पूर्ण
PC का कार्य प्रगति पर ।
-- as on 25-Jun-2024
Physical Peramenters