Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
69W364 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली सं0 38302 दिनांक 25 अक्टूबर 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 121.44 Lacs
Resanction Cost : 121.44 Lacs
Exp. Upto Last Fy : 2.88 Lacs
For CFY 2024-2025
Remaining : 118.56 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.88 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 3 weeks ago
25 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। कार्य प्रगति पर। -- as on 08-Apr-2024
Physical Peramenters