Work Profile Report [69W389]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-पत्रावली सं0 36086 लोक निर्माण अनुभाग-2 देहरादून दि0 27.01.2025
TS Amount (lakhs) : 106.14 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
106.14
Resanction Cost :
106.14
Tentative Cost :
106.14
Exp. Upto Last Fy :
0.16
For CFY 2025-2026
Remaining :
105.98
Demand :
81.00
Allotment :
29.35
Exp in CFY :
29.35
Total Up to Date Exp :
29.51
Construction Started
Sanction on : 9 months 1 week ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
35 %
Tentative Completion date on : 2 months 6 days from now
10 Jan 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 28-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: