Administrative Approval Detail : ई फाइल सं0 68052/46 दिनांक 25.12.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
237.48
Resanction Cost :
237.48
Tentative Cost :
237.48
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
237.48
Demand :
30.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
in Tendering Stage
Sanction on : 4 weeks 1 day ago
25 Dec 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 10 months 6 days from now
30 Nov 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य की दिनांक 12.01.2026 को तकनीकी बिड खोली जा चुकी है। मूल्यांकन किया जा रहा है। -- as on 15-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: