Work Profile Report [6W125]

बागेश्वर में मउडियार गवातोली मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents

Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008

TS Amount (lakhs) : 441 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

441.00

Resanction Cost :

441.00

Tentative Cost :

441.00

Exp. Upto Last Fy :

414.52

For CFY 2024-2025

Remaining :

26.48

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

414.52

Construction Started

Sanction on : 16 years 3 weeks ago

25 Jul 2008

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 1 year 4 months from now

31 Dec 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
12
12
7.750
4.25
0.000
0.000

Remark

view all

7.75 किमी पहाड़ कटान एवं पार्ट 2 का कार्य पूर्ण।
पुनरीक्षित आगणन 12 किमी0 हेतु मुख्य अभियंता के पत्र सं0 166/507 याता0-अ0/2023 दिनांक 09.02.2023 द्वारा लागत 525.94 लाख का स्वीकृति हेतु शासन को प्रेषित।
-- as on 14-Apr-2024

Rating : 112

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Sanction Required form Govt

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: 60 Meter Span steel girder Motor bridge

© PWD Uttarakhand