Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
No of Bridges | 2 | 2 | 0 | 2 | 0 | 0 |
6W187 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 7326(1)111(2)/10-18(प्रा0आ0) 2010टी0सी0-बी0आई0 दिनांक 31 दिसम्बर, 2010
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 63.00 Lacs
Resanction Cost : 63.00 Lacs
Exp. Upto Last Fy : 9.83 Lacs
For CFY 2024-2025
Remaining : 53.17 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.83 Lacs
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
13 years 4 months ago
31 Dec 2010
Tentative Completion date:
1 year 2 months from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
मुआवजा वितरित किया जाना है। कब्जा सत्यापित किए जाने की कार्यवाही प्रगति पर है। -- as on 04-Aug-2023
Physical Peramenters