Work Profile Report [6W367]

जनपद बागेश्वर के विधानसभा क्षेत्र कपकेाट में ढालन खुनौली मोटर मार्ग का चैरा तक विस्तार 3 किमी0
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं0 1152(1)/111(2)/14-62 (प्रा0आ0) /2013 दिनांक 21.02.2014

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

17.55

Resanction Cost :

17.55

Tentative Cost :

17.55

Exp. Upto Last Fy :

3.19

For CFY 2024-2025

Remaining :

14.36

Demand :

2.41

Allotment :

0.61

Exp in CFY :

0.61

Total Up to Date Exp :

3.80

Survey work done

Sanction on : 10 years 10 months ago

21 Feb 2014

Physical Progress:

At start of FY 2024-2025 :

2 %

Up to Date :

15 %

Tentative Completion date on : 8 months 6 days from now

31 Aug 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

समरेखण प्रस्ताव इस कार्यालय के पत्र सं0 2374/1सी0 दिनांक 21.10.2024 द्वारा अनुमोदन हेतु अधीक्षण अभियंता को प्रेषित। -- as on 23-Oct-2024

Rating : 25

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand