Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.25 | 1.25 | 0.000 | 1.25 | 0.000 | 0.000 |
6W379 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 667/111(2)/15-58 (प्रा0आ0)/2014 दिनांक 23.01.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.94
Resanction Cost :
17.94
Tentative Cost :
17.94
Exp. Upto Last Fy : 2.52
For CFY 2024-2025
Remaining : 15.42
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.52
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
9 years 5 months ago
23 Jan 2015
Tentative Completion date:
1 year 1 week from now
31 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
गांव में उपस्थित काश्तकारों का मुआवजा बांटा जा चुका है अवशेष हेतु कार्यवाही प्रगति पर है। -- as on 04-Aug-2023
Physical Peramenters