Administrative Approval Detail : शा0सं0 4417/111(2)/15-04(मु0मं0घो0)/2015 दिनांक 27.05.2015
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.20
Resanction Cost :
30.20
Tentative Cost :
16.60
Saving
13.60
Exp. Upto Last Fy :
10.60
For CFY 2025-2026
Remaining :
19.60
Demand :
4.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
10.60
Phase1 DPR Submitted
Sanction on : 10 years 7 months ago
27 May 2015
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 8 months 3 weeks from now
30 Sep 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 13.6 has been recorded as expected cost of work reduced from 30.2 to 16.60 . -- as on 18-Dec-2025