Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
6W406 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4417/111(2)/15-04(मु0मं0घो0)/2015 दिनांक 27.05.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 48.32 Lacs
Resanction Cost : 48.32 Lacs
Exp. Upto Last Fy : 18.08 Lacs
For CFY 2024-2025
Remaining : 30.24 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 18.08 Lacs
Phase1 DPR Submitted
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
8 years 11 months ago
27 May 2015
Tentative Completion date:
1 year 5 months from now
31 Oct 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
मुआवजा वितरित किया जाना है। -- as on 04-Apr-2022
Physical Peramenters