Work Profile Report [6W413]

मा0मुख्यमंत्री घोषणा 665/2015 के अन्तर्गत दाडिमखेत से कन्यालीकोट मोटर मार्ग में मिलान कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सं0 4417/ंंें111(2)/15-04(मु0मं0घो0)/2015 दिनांक 27.05.2015

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

35.60

Resanction Cost :

35.60

Tentative Cost :

35.60

Exp. Upto Last Fy :

0.70

For CFY 2024-2025

Remaining :

34.90

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.70

Alignment Approved

Sanction on : 9 years 6 months ago

27 May 2015

Physical Progress:

At start of FY 2024-2025 :

52 %

Up to Date :

52 %

Tentative Completion date on : 10 months 6 days from now

31 Oct 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.000
0.000

Remark

view all

सैद्धान्तिक स्वीकृति दिनांक 07.03.2024 को प्राप्त। इस कार्यालय के पत्र सं0 761ध्2ई0 दिनांक 12.03.2024 द्वारा एन0पी0वी0, क्षतिपूरक वृक्षारोपण आदि की धनराशि जमा किए जाने हेतु डिमाण्ड नोट प्रेषण हेतु पत्र लिखा गया है। -- as on 27-Apr-2024

Rating : 62

Forest Case Pending At : 12: AIP DM

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: