Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
6W466 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5988/111(2)/15-11(मु0मं0घो0)/2015 दिनांक 8 अगस्त, 2015
TS Amount (lakhs) : 37.65 Lacs
Financial Detail
Sanction Cost : 55.00 Lacs
Resanction Cost : 55.00 Lacs
Exp. Upto Last Fy : 9.15 Lacs
For CFY 2024-2025
Remaining : 45.85 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 9.15 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
8 years 9 months ago
08 Aug 2015
Tentative Completion date:
11 months 1 week from now
01 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
मुआवजा वितरण की कार्यवाही की जा रही है। -- as on 06-Mar-2023
Physical Peramenters