Work Profile Report [6W473]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 429/111(2)/16-58(प्रा0आ0)/2013 टी0सी0 दिनांक 23 जनवरी, 2016
TS Amount (lakhs) : 3.05 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.80
Resanction Cost :
32.80
Tentative Cost :
32.80
Exp. Upto Last Fy :
8.71
For CFY 2025-2026
Remaining :
24.09
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.71
Phase1 DPR Submitted
Sanction on : 9 years 11 months ago
23 Jan 2016
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 11 months 3 weeks from now
30 Dec 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पहाड़ कटान उपरान्त मुआवजा वितरित किया जाना है।
मुआवजा प्रस्ताव गठित किया जा रहा है।
-- as on 28-Nov-2025