Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
6W690 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ‘शा.सं. 5300/।।।(2)/21- 46(एम0एल0ए0)/2017 टी0सी0प्ट दिनांक 01.11.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
20.40
Resanction Cost :
20.40
Tentative Cost :
20.40
Exp. Upto Last Fy : 0.01
For CFY 2024-2025
Remaining : 20.39
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.01
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
2 years 8 months ago
01 Nov 2021
Tentative Completion date:
1 year 4 months from now
30 Nov 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण प्रस्ताव अनुमोदित। पेडो की गिनती कर ली गई है। दिनाक 28दिसंबर 2023 को संयुक्त निरक्षण वन विभाग राजस्व विभाग के साथ किया गया जिसमे 1.6 किलोमीटर की लंबाई मे सकन्युदा ग्राम संयोजकता प्राप्त हो रही है जिसमे केवल नाप भूमि ही प्रभावित हो रही है।स्टेज 1 का आगणन गठित किया जा रहा है। -- as on 01-Feb-2024
Physical Peramenters